Site Overview
Dahej PCPIR, Gujarat.
30 acresTotal allotted plot (phased build-out)
10 MVAPower capacity at full build-out
50 KL/dayDI water capacity
500mHazmat safety buffer to residential zones
Facility Zones
Purpose-built infrastructure, by function.
🧪
Gas Purification Block
PSA/TSA adsorption columns, catalytic purification reactors, cryogenic distillation unit, multi-stage filtration down to 0.01 μm, ppb-level moisture and O₂ analyzers. Full stack: TSA → catalytic → PSA → final filter.
🛢️
Cylinder & Container Operations
Cylinder inspection, cleaning, and hydro-testing bay. Vacuum manifold filling stations. RFID-tracked cylinder fleet across 500+ units, plus 20 ton containers.
🔬
Analytical QC Laboratory
GC-TCD/FID/PDD, Residual Gas Analyzer, FTIR spectrometer, sub-ppb moisture analyzer, particle counter, ICP-MS for metallic trace impurities.
💎
Crystal Growth & Wafering
CZ pullers for silicon, PVT furnaces for SiC, multi-wire saws, lapping and CMP polishing lines, full wafer metrology suite (XRD, LLS, CV profiler).
🛡️
Safety & Emergency Systems
Toxic Gas Monitoring across the site, emergency scrubber systems for F₂/HF/Cl₂, deluge systems, dedicated Emergency Response Team on-site.
⚡
Utilities
In-house nitrogen backup system, ultra-pure water plant, compressed clean dry air, diesel generator backup for zero fill interruption.
Capacity by Phase
Projected output as we scale.
| Phase | Gas Output | Wafer Output |
|---|---|---|
| Phase 1 (2026–27) | ~500 cylinders/month equivalent | — |
| Phase 2 (2028) | ~1,500 cylinder-equivalents/month | 5,000 wafers/month (150mm Si) |
| Phase 3 (2029–30) | Bulk + synthesis at scale | 15,000+ wafers/month (200mm Si + SiC) |
Environmental Approach
Operating responsibly in a hazmat zone.
💧
Water Treatment & Recycling
Closed-loop DI water recovery targeted for cleaning and CMP processes, reducing freshwater draw from the PCPIR supply.
🌬️
Emissions Control
Scrubber systems on all process exhaust streams before release, monitored continuously against PCB consent limits.
🗑️
Hazardous Waste Management
Licensed hazardous waste handling and disposal through SPCB-authorised contractors, with full manifest tracking.
Security & Access
Controlled by design.
01
Perimeter Security
Fenced perimeter with CCTV coverage across all process and storage areas, monitored 24/7.
02
Access Control
Badge-controlled entry to hazmat storage and process zones, with visitor logging for facility tours.
03
Road & Logistics Access
Direct 4-lane connectivity to the national highway network and Dahej port for both inbound feedstock and outbound delivery.
Build-Out Timeline
From land allotment to full production.
Months 1–6
Land Allotment & Licensing
GIDC land allotment, PESO application filed, Factory License applied, entity incorporation.
Months 6–12
Civil Construction
Plant building and warehouse construction. Purification equipment and cylinder fleet procurement.
Months 12–18
Commissioning & First Deliveries
Lab calibration, internal QC validation runs, first commercial gas deliveries to anchor customers.
Months 18–36
Wafer Line + Phase 2 Chemicals
Wafer pilot line construction and qualification. Blending and wet chemical operations scale up.
Months 36–60
NF₃ Synthesis & Full Capacity
Process gas synthesis plant construction. Wafer lines reach full-scale volume production.
Want a facility tour or technical walkthrough?